Odoo BOM revisions for make-to-order engineering
An engineering firm running Odoo Manufacturing has one question before it turns on revision control: when a drawing changes, does every order on the floor change with it. In Odoo the answer sits in the bill of materials (BoM) and the engineering change order (ECO) that revises it. The production BoM is copied, the copy takes the next version number, and it becomes production only when someone with authority applies it.
A revision is a copy, not an edit
The tempting shortcut is to open the BoM and change the component list. That overwrites the template every new order copies from, and leaves no record of what the previous version contained.
An ECO in the PLM app works the other way. Start Revision stores a copy of the production BoM against the change order and gives it the next version number, V2, V3 and so on. The production BoM stays live while the copy is edited, so a test build or a substitution is worked through without the shop floor seeing either.
When the change is approved, Apply Changes archives the original BoM and the revised version takes over. The Version field on the BoM moves to match. Odoo's engineering change order documentation sets out the sequence, and its PLM feature page says operators see the latest approved BoM on new manufacturing processes. Both were checked on 20 November 2026.
What happens to the orders already on the floor
A manufacturing order is raised from a BoM at a point in time, and it keeps the composition it was raised with. Odoo's PLM feature page puts it plainly: existing and ongoing manufacturing orders continue using the old BoMs, to avoid disruption.
Draft orders are the exception it names: they can be moved to the newly approved BoM with a single click, which suits an order raised yesterday and not yet started.
Ask the implementer to walk that boundary in a test database before the first live revision: an order in draft, one confirmed, one with material issued, one partly built. Write down which state moves and which holds. No configuration screen tells you that in advance.
The habit to avoid is cancelling an order so it can be rebuilt on the new revision. Odoo's MTO documentation says a cancelled manufacturing order is not automatically replaced, and a manual replacement cannot be linked back to the original sales order. Update the order instead.
The drawing has to travel with the BoM
Revision control that lives in a folder beside Odoo is not revision control. Design files attach to the BoM itself, and an ECO carries its own Documents set: CAD files, PDFs, worksheets, images. New files link to the production BoM on apply. Removed files are archived, not deleted, and stay readable in the ECO.
That matters when a fitter asks which drawing the job was built to. The answer should be the file on the version, not the latest email.
Who signs, and on which stage
An ECO moves through stages. Odoo's defaults are New, In Progress, Validated and Effective, editable per ECO type. A verification stage carries approvers: a role, a user, and an approval type of required, optional or comments only.
One detail deserves a check. Odoo's approvals documentation warns that if no approver on the stage is set to Is required to approve, Apply Changes works without anyone pressing Approve. A stage with only optional approvers is not a gate.
Decide which changes need which route. A drawing that alters a purchased component and one that corrects a note should not queue behind the same three people.
Date the change or lose the history
The ECO's Effective field takes As soon as possible or a date. Choose As soon as possible and the revision history carries no dates: Odoo's version control documentation says an empty Effective Date is not recorded against the BoM's revision history.
A date lets the next order pick up the change without reopening the last one. It also answers a customer complaint two years later, when the question is which BoM version was live as a serial was built. Odoo's documentation names recalls and complaints as the reason to keep that history.
Two changes, one BoM
Engineering rarely releases one change at a time. Two ECOs can be open against the same BoM, and applying the first moves production on, leaving the second on an older base. Odoo shows the difference in a Previous ECO BoM Changes tab and offers Apply Rebase, which pulls the first change into the second.
That is a merge, and merges need an owner. Name the person who decides when a rebase is correct and when the older change should be withdrawn.
The settings that carry the control
| ECO field | What it decides | The default to question |
|---|---|---|
| Apply on | Whether the change touches the BoM or the product record only | A product-only change will not move the component list |
| Effective | Whether the change applies at once or from a date | As soon as possible leaves the revision history undated |
| Type and stage | Which route the change takes and who must approve | A stage with no required approver does not block Apply Changes |
| Revision | The version number the copy receives at Start Revision | Numbering starts at V2 on the first revision |
| Documents | Which drawings and files travel with the change | Archived files stay in the ECO, so the old drawing remains readable |
What to settle before the first revision
- 01Who owns the BoM, and whether that person also approves changes to it.
- 02Which ECO types you need. One type for everything puts a drawing correction behind a new product introduction.
- 03Whether drawings live in Odoo or in a separate document system, and how the current revision is marked in each.
- 04What happens to a confirmed order when a change is applied, per order state rather than in conversation.
- 05Whether PLM is installed. Odoo's documentation says it is not installed with Manufacturing by default.
What to check in a demo
Bring a job revised twice after release. Ask for the BoM before the first change, the ECO that changed it, the drawing on each version, and the order that was on the floor. Then ask what that order shows now.
If the answer needs a screenshot from last month, the revision history is not doing its job. The engineering page covers the wider project, change and cost picture. The cost side of a component change is on when a supplier price changes a cost. We implement Odoo with our technical partners, who scope this against a live job.
I sincerely hope this was helpful, and if you have any remark, suggestion or question, you can email me at louis@cdb.solutions or DM me on LinkedIn.
Thank you,
Clovis
Next step
See this in practice
Book a free demo. The technical partner for your country shows the apps that fit, at no charge.
Canonical URL: https://www.cdb.solutions/articles/engineering-bom-revisions
FAQ
Answers to the questions this article raises
The questions buyers ask most, answered here. If yours is not covered, ask us directly.
01Does revising a BoM change manufacturing orders that are already running?
02Do we need the PLM app for BoM versioning?
03Can we go back to a previous BoM version?
04How do we prove which revision a delivered job was built to?
Next step
Book a free demo
Tell us the country and the operation. The technical partner for your country shows Odoo against your process, at no charge.
+33 7 69 45 83 27UK with SofthealerEverywhere else with AppNvent
Free demo
Put this against your own operation
Country, industry and company size. The technical partner scopes the work and holds the agreement.
Country chooses the partner. The UK is implemented with Softhealer. Everywhere else, with AppNvent.
The demo is specific. Industry and company size tell the technical partner which apps to show you.
No charge, no obligation. Scoping and any agreement come later, and only if you want them.